How to work it out
Pavers
Area × pavers per m² (50 per m² for 200 × 100), plus an allowance for cuts and breakages: 5% for stretcher bond or stack, 7% for herringbone square to the edges and 10% for herringbone at 45°.
Base and bedding
Patios and paths usually get 100 mm of compacted AP40 basecourse and driveways 150 mm, with 30 mm of screeded bedding sand on top. Basecourse compacts down, so Takeoff buys about 30% more loose than the finished depth.
Edges
Pavers need holding in on every open edge or they creep and the sand washes out. Takeoff measures the edges that aren’t against the house and lists a concrete haunch, plastic edging with spikes, or H4 timber boards and pegs.
Joint sand and hire
Joint sand is worked out from the length of joint between pavers, their depth and the joint width. A plate compactor (with a rubber mat for the pavers) and a paver saw or splitter are listed as hire.
Worked example
A 5 × 4 m patio against the house, 200 × 100 × 60 mm pavers in stretcher bond, 30 mm of bedding sand on 100 mm of compacted AP40, with a concrete haunch round the open edges. Everything else is on the default settings.
| Item | Qty |
|---|---|
| Pavers | |
| Pavers200 × 100 × 60 mm · 20 m² + 5% for cuts & breakages · 50 per m² | 1050 pavers |
| Bedding | |
| Bedding sandScreeded 30 mm · loose · 0.69 m³ incl. 15% for screeding & levels | 0.7 m³ |
| Base | |
| BasecourseAP40 (GAP40) · loose, compacted in layers · 100 mm compacted · 2.6 m³ loose | 2.6 m³ |
| Geotextile clothNon-woven, under the basecourse · 20 m² + 15% for laps and edges — sold off the roll by the metre | 23 m² |
| Edges | |
| Concrete for the edge haunch20 kg premix concrete bags · 13 m of edge · ≈150 × 150 mm haunch | 19 bags |
| Joints | |
| Jointing sandKiln-dried, fine · 20 kg bags · ≈105 kg for 300 m of 3 mm joints, plus top-ups | 6 bags |
| Hire | |
| Plate compactor hireVibrating plate, with a rubber mat for the pavers · Compact the base in 50–75 mm layers, then bed the pavers in | 1 day |
| Paver splitter or saw hireDiamond blade saw for clean cuts · For the edge cuts | 1 day |
This is the list Takeoff produced for that job. Your list will change with your sizes and settings.
Check before you buy
- Dig out about 190 mm below the finished paving (paver 60 + bedding 30 + basecourse 100 mm). That’s roughly 4.8 m³ of soil — about 8 trailer loads, or a skip.
- Give the paving a fall of about 1 in 60 (17 mm per metre) away from the house, and keep the finished level at least 150 mm below the floor level of the house (or as your cladding requires).
What the calculator covers
- Several patios, paths or drives in one list
- Brick-style pavers through to 600 × 600 slabs, or your own size
- Stretcher bond, stack and herringbone
- Laying on the ground or onto an existing slab
- Sand or mortar bedding
- AP40 basecourse, bulk by the m³ or in bags
- Concrete, plastic or timber edge restraint
- Kiln-dried or polymeric joint sand
- Dig-out depth and how much soil to remove
Questions
How many pavers do I need per square metre?
Divide 1 m² by the size of one paver: 200 × 100 pavers are 50 per m², 300 × 300 about 11, and 600 × 600 about 2.8. Then add 5–10% for cuts and breakages depending on the pattern.
How deep do I dig for pavers?
Add the paver thickness, about 30 mm of bedding sand and the basecourse: typically about 190 mm for a patio (60 + 30 + 100) and 240 mm for a driveway (60 + 30 + 150). Takeoff shows the depth and the soil to remove.
How much basecourse do I need?
Area × compacted depth, plus about 30% because it compacts. A 20 m² patio at 100 mm needs about 2.6 m³ of loose AP40.
Can I lay pavers on a driveway?
Yes — use pavers at least 60 mm thick (80 mm for heavier vehicles), a deeper base, and a herringbone pattern so they lock together. Large slabs usually crack under cars unless they’re on concrete.